Projects
Beautification:
The walkway to the boat ramp area from Hibiscus Road is being addressed. The area will be trimmed and cleaned up. In addition, the fences along the area, currently in disrepair, are being replaced. Vandalized shrubs along the Hibiscus tidal gut have been cleaned up.

Road Replacement / Drainage:
A contractor has been engaged to complete Holly, Sunrise Shore, Shell and miscellaneous potholes with work to commence May 2017. Several additional drains to be installed on roads and boat ramp.

Boat Ramp Area:
Some trees were removed (SEP 2016) and clean-up performed after "Mathew" and a major Northeaster. Six Geotubes are in place to contain and drain the dredging spoils. Additional drainage improvements and grading to be performed once the spoils from dredging have been removed. We have requested boat ramp repair bids with 3 different options for consideration to be completed in 2017.

Bulkheads:
Hibiscus community bulkhead is deteriorating and will be repaired (approximately 80 feet). Currently out for bid. Community bulkhead on Coral Court and Sunrise Drive are also in need of repair. 3 private bulkhead owners have been notified regarding required repairs and have yet to respond.

Dredging:
Silted-in areas of the community canals were dredged in late 2016. The spoils were drained in the boat ramp area in "Geotubes" and subsequently removed (spring 2017). Further regrading, additional drains and plantings were installed in the area.   All work was permitted through the appropriate government agencies. Please see additional information on the "Info" page.